Question: QUESTION 6 Consider a project with many paths, but only a single one is critical: Path BEGIJ. While there are over 20 activities in the

QUESTION 6 Consider a project with many paths, but only a single one is critical: Path BEGIJ. While there are over 20 activities in the project the only ones that are crashable are A, E, H, and I. Their information is given below. Assuming you are going to crash one of them by one period, which one should be your choice? Activity Normal/Minimum Times Crash cost A 8/6 $1,000 E 3/1 $5,000 H 5/4 $2,500 1 12/8 $4,000 a. A b. E . d. 1