Question: - = Question 6 If the time factor is 0 , 3 5 and the c v = 8 . 2 1 0 - 4

-=
Question 6
If the time factor is 0,35 and the cv=8.210-4m2s Calculate the time required for settlement of clay layer of double drainage system.
2
3
4
18 days
(5)
(6)
35 days
7
8
25 dsys
9
10
29 days