Question: QUESTION 6 Individuals were randomly assigned to three different production processes. The hourly units of production for the three processes are shown below. Production Process

QUESTION 6 Individuals were randomly assigned to

QUESTION 6 Individuals were randomly assigned to three different production processes. The hourly units of production for the three processes are shown below. Production Process Process 1 Process 2 Process 3 33 33 28 30 35 36 28 30 30 29 38 34 Use the analysis of variance procedure with a = .05 to determine if there is a significant difference in the mean hourly units of production for the three types of production processes. Report the value of MSTR