Question: Question 6. Six jobs must be processed through machine 1 and then machine 2 as shown below. The processing time for each job is also

Question 6. Six jobs must be processed through
Question 6. Six jobs must be processed through machine 1 and then machine 2 as shown below. The processing time for each job is also shown: (20 points) F kob Number Machine 1 minutes Mochine 2 minutes 10 8 8 9 10 C D 35 9 4 E 5 2 De 7 a) Find the best way to sequence these jobs (use Johnson's rule). b) Prepare a Gantt chart