Question: Question 6 View Policies Current Attempt in Progress Vest Construction Company's cost of renting a crane for the last four months is as follows: Month

Question 6 View Policies Current Attempt in Progress Vest Construction Company's cost of renting a crane for the last four months is as follows: Month January February March April Hours of Operation Rental Cost $983 $1,112 $1.153 $1.058 Using the high-low method, what is the company's estimated variable and fixed component of operating expenses? per hour Variable cost per hour Fixed cost