Question: QUESTION 6 We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and no precedents.
QUESTION We have a project RaiseL with these activities in days: Activity A with duration and no precedents. Activitywith duration and predecessor. A Activitywith duration and predecessor. A Activity D with duration and predecessor B Activity E has duration and predecessors B and C Activity F has duration and predecessor D and Activity G has duration and predecessors ofand F Draw this to answer the following questions. How long is this project scheduled to take? days days days days. What is the LS for node C
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
