Question: QUESTION 6 We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and no precedents.

QUESTION 6 We have a project (Raise_L), with these activities in days: Activity A with duration 6 and no precedents. Activitywith duration 10 and predecessor. A, Activitywith duration 2 and predecessor. A, Activity D with duration 6 and predecessor B, Activity E has duration 3 and predecessors B and C, Activity F has duration 1 and predecessor D, and Activity G has duration 11 and predecessors ofand F. Draw this to answer the following questions. How long is this project scheduled to take? 22 days 33 days 34 days 39 days. What is the LS for node C