Question: Question 62 Laytime for discharge operations is 08 days 17 hours 20 mins. If the amount used was 06 days Not yet 12 hours and

 Question 62 Laytime for discharge operations is 08 days 17 hours

Question 62 Laytime for discharge operations is 08 days 17 hours 20 mins. If the amount used was 06 days Not yet 12 hours and 56 minutes. Demurrage is $1000.00 and Dispatch rate is 50% of demurrage. answered What is due and how much? Marked out of 1.00 O a. Dispatch of $2191.52 Flag question O b. Demurrage of $2191.52 O c. Dispatch of $1091.72 O d. Demurrage of $1091.72