Question: Question 7 1 0 p t s 1 Using the priority list T 7 , T 5 , T 8 , T 9 , T

Question 7
10pts
1
Using the priority list T7,T5,T8,T9,T4,T2,T3,T6,T1, schedule the project below with two processors.
\table[[Task,Time Required,Tasks that must be completed first],[T1,11,],[T2,7,],[T3,8,],[T4,4,T1],[T5,8,T1, T2],[T6,9,T2, T3],[T7,11,T4, T5],[T8,9,T5],[T9,6,T5, T6]]
Task 5 is done by
starting at time
Task 8 is done by
starting at time
The finishing time for the schedule is