Question: Question 7 : ( 1 5 marks ) Line Balancing Fisher and Paykel Appliances, a NZ based company is working on a building washing machines
Question : marks Line Balancing
Fisher and Paykel Appliances, a NZ based company is working on a building washing machines for a European market. After conducting a market survey, the demand forecast for the year was estimated. To meet the demand, the production line should be capable of producing washing machines a day. A typical work shift for workers is hours per day. Select in alphabetical order. Balance the line to meet the demand.
a Draw precedence chart.
b Calculate the cycle time and theoretical minimum number of workstations to meet the demand.
c Calculate efficiency.
tableTaskTask time SECONDSPrecedenceABABCCDDEDEFE FGG