Question: Question 7 ( 1 point ) Information on Hanley's direct labor costs for April is as follows: Actual direct labor rate - $ 9 .

Question 7(1 point)
Information on Hanley's direct labor costs for April is as follows:
Actual direct labor rate - $9.50? hour
Budgeted hours -15,000 hours
Actual hours -16,000 hours
Direct labor rate variance -$8,000(U)
Determine Hanley's budgeted direct labor rate per hour for April.