Question: Question 7 1 Point The project definition is a key step which is usually identified during the stage: A Closing stage B Controlling stage C

Question 7 1 Point The project definition is a

Question 7 1 Point The project definition is a key step which is usually identified during the stage: A Closing stage B Controlling stage C Planning stage Scheduling stage Question 8 1 Point The project critical path is : A The group of activates that help to finish the project in shortest time. B The group of activities within a project that have slack time. A sequence of activities that has the longest time duration within a project. The shortest path from the first activity to project end