Question: Question 7 1 pts Activity C has the earliest start ( ES ) time of 8 , earliest finish ( EF ) time of 1

Question 7
1 pts
Activity C has the earliest start (ES) time of 8, earliest finish (EF) time of 15, latest start (LS) time of 17, and latest finish (LF) time of 24. Its slack is ...
4.
5.
0.
9.
1.
Question 8
1pt
The critical path is the longest-duration path in a project.
q,
True
False
 Question 7 1 pts Activity C has the earliest start (ES)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer