Question: Question 7 1 pts During a project, earned value analysis is performed, resulting in the following numbers: EV: 523,000 PV: 623,000 AC: 643.000 Which results

Question 7 1 pts During a project, earned value
Question 7 1 pts During a project, earned value analysis is performed, resulting in the following numbers: EV: 523,000 PV: 623,000 AC: 643.000 Which results are correct? CV:-120,000; SV: -100,000 OCV:-100,000; SV: -120,000 O CV: +100,000; SV: +120,000 CV: +120,000: SV: +100,000