Question: Question 7 1 pts Processes used to formally complete or close a project or phase fall within which project management process group? closing O finalizing

Question 7 1 pts Processes used to formally
Question 7 1 pts Processes used to formally complete or close a project or phase fall within which project management process group? closing O finalizing monitoring and controlling O delivering Question 8 1 pts Processes used to track, review, and regulate the progress and performance of the project and manage changes fall within which project management process group? O measuring closing reviewing O monitoring and controlling