Question: Question 7 10 Points You are faced with a task for designing and manufacturing a new product. Table 8.1 shows a set of tasks,
Question 7 10 Points You are faced with a task for designing and manufacturing a new product. Table 8.1 shows a set of tasks, their predecessors, and optimistic, most likely, and pessimistic durations for each activity involved in the production of this new product. Table 8.1 Important activities for the development of a new product Activity Predecessor Optimistic Most likely A 8 10 Pessimistic 16 B A 11 12 14 C B 7 12 19 D B 6 6 6 E B 10 14 20 F CD D G H E, G 60 5 4 10 10 1. Determine the critical path, using the expected activity times. Blank 1 2. What is the probability of completing the project within week 50? Blank 2 10 17 11 8