Question: Question 7: (15 points) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected
Question 7: (15 points) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows:
Year Project A Cash Flow Project B cash Flow
0 (110,000) (110,000)
1 30,000 0
2 30,000 0
3 30,000 0
4 30,000 0
5 30,000 210,000
If the appropriate discount rate on these projects is 11 percent, which would be chosen and why? (Round to the nearest cent.)
a. The NPV of Project A is: $
b. The NPV of Project B is: $ Which project would be chosen and why? (Select the best choice below.)
a. Cannor choose without comparing their IRRs.
b. Choose A because its NPV is higher.
c. Choose both because they both have positive NPVs.
d. Choose B because its NPV is higher.