Question: Question 7 3 . 0 3 p t s Find the maximum number of weeks that activity C can be delayed without delaying the project.
Question
Find the maximum number of weeks that activity can be delayed without delaying the project.
Question
pts
Which of the following actions leads to a twoweek reduction in the project duration?
Shorten B by week and D by week
Delay by week and shorten by week
Delay A by week and shorten G by week
Shorten E by week and G by week
Shorten by week and by week