Question: Question 7 / 3 0 AB , C , D and ED , E . B . A aadEWhat is the most appropriate sequence in

Question 7/30AB, C,D and ED,E. B. A aadEWhat is the most appropriate sequence in which the following steps should be performed by ProjectManager (PM) for receiving CSS? A) Orient the Customer on the CSs process B) ldentify Customermanagers to whom the survey needs to be sent C) Set CSS Applicability, Feedback Format andCalendar for the project D) Initiate CSS survey invite E) Highlight the key value additions andmilestones accomplished during the feedback period to the Customer ManagerSelect the correct option(s) ond click submit.CB, E, A and DA CE B and D4/30 CorrectSubmitO 32:9L1b2133