Question: Question 7 4 p t s The demand the forecast for the last five months are given below. Calculate the root mean square deviation (

Question 7
4pts
The demand the forecast for the last five months are given below. Calculate the root mean square deviation (RMSD).
(Calculate the MSD and then take the root)
\table[[Month,Demand,Forecast],[January,221,237],[February,230,230],[March,236,217],[April,226,233],[May,217,214]]