Question: Question 7 5 points Save Answer ATTENTION: THE PROBLEM LOOKS LIKE THE PREVIOUS ONE BUT THE NUMBERS AND THE QUESTION IS DIFFERENT The month of

Question 7 5 points Save Answer ATTENTION: THE PROBLEM LOOKS LIKE THE PREVIOUS ONE BUT THE NUMBERS AND THE QUESTION IS DIFFERENT The month of June just came to an end, which was the 6th month in a 20 month project with a BAC of $95M that you are managing. You just received the following cumulative cost measurements: BCWS = $27M, BCWP = $47M; ACWP - $62M What is the To Complete Performance Index based on Budget at Completion? Note: M stands for Million. While giving your answers you do not need to write the units. For example; simply write 80.25 for $80.25M. Please keep two digits after decimal point if necessary
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts