Question: Question 7 (5 points) To shorten project completion time, project managers should allocate resources on non- critical activities on the project network because critical activities

Question 7 (5 points) To shorten project

Question 7 (5 points) To shorten project completion time, project managers should allocate resources on non- critical activities on the project network because critical activities have zero slack resources. a) True b) False Question 8 (5 points) Both Critical Path method (CPM) and Project Evaluation and Review Technique (PERT) assume activities are independently from each other. a) True b) False