Question: QUESTION 7 Assume that below is the given activities table of a project have the following durations (in days) and dependencies. Draw the AON network

QUESTION 7

  1. Assume that below is the given activities table of a project have the following durations (in days) and dependencies. Draw the AON network diagram, list all the paths with total durations, and then find the critical path and its durationQUESTION 7 Assume that below is the given

ALU Activity Predecessor Duration A 2 B A 2 A 3 D A 4 E B 2 F 3 G D 6 H B, C 2 I B, C 5 J 1 K H, J 2 I, G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!