Question: Question 7 Saved When two or more activities terminate in a third, activity, the earliest that the succeeding activity can start is: Question 7 options:

Question 7

Saved

When two or more activities terminate in a third, activity, the earliest that the succeeding activity can start is:

Question 7 options:

When the first activity is completed

When the second activity is completed

When all preceeding activities are completed

Prior to the end of the critical preceeding activity

Question 8

When three activities are scheduled in parallel, the critical path activity will be found on:

Question 8 options:

The shortest duration activity

The longest duration activity

The activity that is most important to the project

The activity that uses the most resources

Question 9

A network diagram condition that can never happen is:

Question 9 options:

All paths are on the critical path

The critical path turns out to be the shortest path

More than three activities occur in parallel

Two activities are found to be in parallel with a third activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!