Question: Question 7 Saved When two or more activities terminate in a third, activity, the earliest that the succeeding activity can start is: Question 7 options:
Question 7
Saved
When two or more activities terminate in a third, activity, the earliest that the succeeding activity can start is:
Question 7 options:
|
| When the first activity is completed |
|
| When the second activity is completed |
|
| When all preceeding activities are completed |
|
| Prior to the end of the critical preceeding activity |
Question 8
When three activities are scheduled in parallel, the critical path activity will be found on:
Question 8 options:
|
| The shortest duration activity |
|
| The longest duration activity |
|
| The activity that is most important to the project |
|
| The activity that uses the most resources |
Question 9
A network diagram condition that can never happen is:
Question 9 options:
|
| All paths are on the critical path |
|
| The critical path turns out to be the shortest path |
|
| More than three activities occur in parallel |
|
| Two activities are found to be in parallel with a third activity |