QUESTION 7
-
The following data is reported by a project manager. He is asking you to analyze the situation and let him know of the needed duration and budget contingency to mitigate the situation at this stage of project?
Note: Use EVM for Cost and EDM for Duration.
TPD: Total Planned Duration
TED: Total Earned Duration
TAD: Total Actual Duration
BPD: Baseline Planned Duration (Project Duration)
PV: Planned Value
EV: Earned Value
AC: Actual Cost
BAC: Bidget At Completion
TPD TED TAD BPD PV EV AC BAC 160 weeks 120 weeks 160 Weeks 60 Weeks 1000 800 1200 2000 a. 80 weeks and $3000
b. 40 weeks and $2800
c. 20 weeks and $1000
.
d. 18 weeks and $800