Question: Question 7 ( Use the information below to solve the following questions ) Given the following information regarding a project: ActivityDurationPredecessorsa 2 Noneb 3 Nonec

Question 7
(Use the information below to solve the following questions)
Given the following information regarding a project:
ActivityDurationPredecessorsa2Noneb3Nonec2ad4a, be4cf3cg5d, eh2f, g
Which of the following is NOT a path in the network?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-h
1 points
Question 8
What is the critical path?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-g
1 points
Question 9
How long will it take to complete the project?
4
9
10
13
15
1 points
Question 10
What is the LS for activity a?
0
1
3
4
5
1 points
Question 11
What is the LF for activity f?
10
13
15
19
1 points
Question 12
What is the EF for activity g?
7
8
10
13
15
1 points
Question 13
What is the LF for activity h?
7
8
10
13
15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!