Question: QUESTION 7 Usually the preferred method for delay analysis (or schedule analysis or schedule implementation analysis) is: A. Collapsed As-Built B. Windows Analysis C. Impacted

QUESTION 7

  1. Usually the preferred method for delay analysis (or schedule analysis or schedule implementation analysis) is:

    A.

    Collapsed As-Built

    B.

    Windows Analysis

    C.

    Impacted As-Planned

    D.

    Contemporaneous Analysis