Question: QUESTION 79 The project completion time is a. 19 weeks. b. 11 weeks. c. 13 weeks. d. 17 weeks. e. indeterminate. QUESTION 80 The critical
QUESTION 79
The project completion time is
a. 19 weeks.
b. 11 weeks.
c. 13 weeks.
d. 17 weeks.
e. indeterminate.
QUESTION 80
The critical activities of the above project are
a. A, D, F.
b. B, D, F
c. A, C, E.
d. A, B, E, F.
e. A, C, E, F
QUESTION 82
What weighted score did the winner(s) receive?
a. 26.0
b. 6.5
c. 32.0
d. 7.25
e. 7.10
QUESTION 83
Not being certain which criterion is more important than another or by how much, select the most favorable vendor without weighting the ratings.
a. A.
b. C.
c. E.
d. B.
e. A and E.
QUESTION 84
What score did the winner(s) receive?
a. 26.0
b. 6.5
c. 32.0
d. 7.25
e. 7.10
79. The table below gives the precedence chart for a project. Precedes Activity A B D E F A AB D Time (weeks) 8 3 7 3 4 6 The project completion time is