Question: Question 7(Mandatory)(1 point) Saved You are a project manager on a project that requires material from a U.S. supplier to be purchased in an ongoing
Question 7(Mandatory)(1 point)
Saved
You are a project manager on a project that requires material from a U.S. supplier to be purchased in an ongoing manner.
You are aware that the Canadian dollar is dropping (and is expected to continue to drop) in value compared with the U.S. dollar.
You wish to avoid the risk of project materials costing more in the future.
Which type of contract would you most likely want to use with your U.S. supplier ?
Question 7 options:
Costs plus contract | |
Fixed price contract | |
Time and materials contract | |
Statement of work contract |
Question 8(Mandatory)(1 point)
Saved
Question 8 options:
The project is behind schedule. | |
The project's costs are below the budgeted costs. | |
The reason PV is shown to the end of the project is that it represents the project's original budget and does not change during execution. | |
The information presented in the graph would only be of interest to other project managers; the project team or other project stakeholders would have no interest in it. | |
Based on the graph, it is obvious that the project must have used the 10/90 rule for determining the project's earned values. |
Question 9(Mandatory)(1 point)
Saved
Question 9 options:
An organization (org) chart | |
A bottom-up look up chart | |
A top-down look up table | |
A responsibility matrix |
Question 10(Mandatory)(1 point)
Saved
What type of project lifecycle does this approach most closely represent?
Question 10 options:
| |||
| |||
| |||
|
Question 11(Mandatory)(1 point)
Saved
The reason that a project manager would select an agile life cycle development appproach over a more traditional approach is:
Question 11 options:
| |||
| |||
| |||
|
Question 12(Mandatory)(1 point)
Saved
What is theActual Cost (AC)of the project on week 4?
Question 12 options:
1250 | |
1300 | |
750 | |
1400 |
Question 13(Mandatory)(1 point)
Saved
Based on the suppliedEARNED VALUE DATA (see question 12):
What is the project's totalEarned Value (EV), as of week 4?
Question 13 options:
1200 | |
1300 | |
1400 | |
1700 |
Question 14(Mandatory)(1 point)
Saved
Based on the suppliedEARNED VALUE DATA (see question 12):
What is the project'sCost Variance (CV), as of week 4?
Question 14 options:
-100 | |
-200 | |
1400 | |
Unable to determine |
Question 15(Mandatory)(1 point)
Saved
Based on the suppliedEARNED VALUE DATA(see question 12):
What is the project'sCost Performance Index (CPI), as of week 4?
Question 15 options:
0.85 | |
0.92 | |
0.52 | |
Unable to calculate CPI based on the information supplied. |
Question 16(Mandatory)(1 point)
Saved
Based on the suppliedEARNED VALUE DATA (see question 12):
What is theSchedule Performance Index (SPI)value for this project?
Question 16 options:
0.86 | |
| 0.92 | |
1.12 | |
Unable to determine the SPI for this project. |
Question 17(Mandatory)(1 point)
Saved
Based on the suppliedEARNED VALUE DATA (see question 12):
What conclusion can be drawn, based on the project's CPI and SPI values?
Question 17 options:
| The project's CPI and SPI values indicate that the projectis over budget and behind schedule.
| |
The project's CPI and SPI values indicate that the projectis under budget and ahead of schedule. | |
The project's CPI and SPI values indicate that the projectis on budget and on schedule. | |
No conclusions can be drawn from this project's CPI and SPI values. |
Question 18(Mandatory)(1 point)
Saved
What is the overall duration of this project?
| 4 | 4 | 8 | |||||||||||||||||||||
| | Task C | ||||||||||||||||||||||
| 0 | 4 | 6 | 2 | 10 | |||||||||||||||||||
| Task A | |||||||||||||||||||||||
| 1 | 1 | 5 | 5 | 5 | 10 | 2 | |||||||||||||||||
| Task D | Task D | ||||||||||||||||||||||
| 0 | 5 | 5 | 5 | 10 | 10 | 0 | |||||||||||||||||
| Task B | |||||||||||||||||||||||
| 0 | 0 | 5 | 5 | 3 | 8 | Legend | |||||||||||||||||
| Task E | ES | Dur | EF | ||||||||||||||||||||
| 7 | 0 | 10 | Task Name | ||||||||||||||||||||
| LS | Slack | LF | |||||||||||||||||||||
Question 18 options:
| |||
| |||
| |||
|
Question 19(Mandatory)(1 point)
Saved
Based on the suppliedNETWORK DIAGRAM (see question 18):
What is the project's critical path?
Question 19 options:
| |||
| |||
| |||
|
Question 20(Mandatory)(1 point)
Saved
Based on the suppliedNETWORK DIAGRAM (see question 18):
What is the Early Finish (EF) for task A?
Question 20 options:
4 | |
6 | |
1 | |
5 |
Question 21(Mandatory)(1 point)
Saved
Based on the suppliedNETWORK DIAGRAM (see question 18):
What is the slack for task D?
Question 21 options:
0 | |
5 | |
10 | |
3 |
Question 22(Mandatory)(1 point)
Saved
Which one of the following inputs (information, event or consideration) doesnotimpact the initial planning process for the project schedule?
Question 22 options:
| |||
| |||
| |||
| |||
| |||
| |||
| |||
|
Question 23(Mandatory)(1 point)
Saved
Question 23 options:
| |||
| |||
| |||
| |||
| |||
| |||
|
Question 24(Mandatory)(1 point)
Saved
Creating a WBS can be very complicated, and as project managers, we are often left wondering if we have decomposed the project sufficiently to proceed with its planning.
Which of the following isnota criterion for determining if your WBS is complete?
Question 24 options:
| |||
| |||
| |||
| |||
|
Question 25(Mandatory)(1 point)
Saved
A project WBS is key to understanding a project - however, not all elements of a project are dependent upon a project WBS.
Which one of the following isnotinfluenced by the project's WBS?
Question 25 options:
| |||
| |||
| |||
| |||
|
Question 26(Mandatory)(1 point)
Saved
Using the three point estimating technique - what is the expected duration for Task A?
Question 26 options:
10 days | |
14 days | |
14.3 days | |
14.7 days |
Question 27(Mandatory)(1 point)
Saved
Based on the suppliedESTIMATING DATA (see question 26):
Using the three point estimating technique - what is the expected duration for task E?
Question 27 options:
7 1/3 days | |
7 5/6 days | |
10 1/3 days | |
23 days |
Submit Quiz27 of 27 questions saved
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
