Question: Question 8 (1 point) J/ / f x _-e_ Given the diagram above, which two activities can you fast track to shorten the schedLe? 1:)

 Question 8 (1 point) J/ / f \\x _-e_ Given thediagram above, which two activities can you fast track to shorten theschedLe? 1:) A & C If") B & C \\_ C}C&E (}A&B\\_ Question 9 (1 point] Activity Duration weeks Given the table, whatis the duration of the project? _'\\ J 2 weeks :CC _

Question 8 (1 point) J/ / f \\x _-e_ Given the diagram above, which two activities can you fast track to shorten the schedLe? 1:) A & C If") B & C \\_ C}C&E (}A&B \\_ Question 9 (1 point] Activity Duration weeks Given the table, what is the duration of the project? _'\\ J 2 weeks :CC _ 5 weeks 2 28 weeks 2 3 CC 3 weeks Activity Predec- Early Late | Early Late Number Activity Duration Jessor Start Start Finish Finish 1 31 4 5 6 8 9 10 11 12 13 1 A 1 1 3 B 1 2 3 2 3 2 C IN 1 2 2 A D 3 2 & 3 4 6 E 2 4 7 9 8 10 4 4 7 10 G 3 5 & 6 11 13 Notes: End weeks use the PMBOK Guide 6th ed. convention. Predecessor refers to activity numberActivity Predec-Early Late Early Late Number Activity Duration essor Start Start Finish Finish 1 2 3 4 5 61 7 8 9 10 11 12 13 1 A 1 1 1 W B 1 2 3 2 3 2 C 1 2 2 D 3 2 & 3 4 6 6 E 4 7 9 8 10 5 WAN 4 7 10 7 G 5 & 6 11 13 Notes: End weeks use the PMBOK Guide 6th ed. convention. Predecessor refers to activity number2 B D 4 START A E END Activity Method Reduction (weeks) Cost A Crash $7,000 B-D Fast Track 2 $12,000 C Crash $8,000 E Crash $9,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!