Question: Question 8 (1 point) The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,800 units, the
Question 8 (1 point) The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,800 units, the actual direct labor cost was $48,000 for 3,000 direct labor hours worked, the total direct labor variance is a) $1,800 unfavorable. Ob) $3,750 unfavorable. Oc) $6,000 favorable. Od) $6,000 unfavorable