Question: Question 8 1 pts A project has an up-front cost of $100,000. The project's required return is 12 percent and its net present value is
Question 8 1 pts A project has an up-front cost of $100,000. The project's required return is 12 percent and its net present value is $10,000. Which of the following statements is most correct? The project should be rejected since its return is less than the required return The project's internal rate of return is greater than 12 percent The project's modified internal rate of return is less than 12 percent. O All of these answers are correct. O None of these answers are correct. 1 pts Question 9 which will yield cash