Question: QUESTION 8 10 points Save Answer Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the

 QUESTION 8 10 points Save Answer Ehrmann Data Systems is considering

QUESTION 8 10 points Save Answer Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's projected MIRR can be less than the WACC (and even negative), in which case it will be rejected. WACC 7.7596 1 Year 0 $1,000$450$450 $450 3 2 a. 13.38% b. 14.04% c. 14.58% d. 14.18% Oe. 16.72% Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answers Close Window Save and Submit