Question: Question 8 5 pts When there is a 3 - day lag between the end of activity A and the start of activity B ,
Question
pts
When there is a day lag between the end of activity A and the start of activity then:
Activity has to wait exactly days after the completion of activity A before it can start.
b Activity has to wait at least days after the completion of activity A before it can start.
c Activity B has to wait at most days after the completion of activity A before it can start.
d Activity B eannet take more than days in duration.