Question: Question 8 A project manager has just been given a project that has a specific completion date. After a discussion with top management, they are
Question
A project manager has just been given a project that has a specific completion date. After a discussion with top management, they are told that while the date is important, the cost is more important, and a delay in the project completion date would be fine, if needed to meet the cost targets. The completion date is best classified as a criterion that has been
accepted
enhanced
constrained
altered