Question: Question 8 If there is no completion date specified in the contract, the Contractor: will have no legal responsibilty for failing to complete the work
Question
If there is no completion date specified in the contract, the Contractor:
will have no legal responsibilty for failing to complete the work within any particular time.
will be required to justify the time taken upon filing of a formal complaint by a party to the
contract.
is required to complete the work within a reasonable time.
will be required to complete the work by the time reasonably set in written notice from the
Owner.