Question: Question 8 (Mandatory) (1 point) If you change your project management plan in such a way that a risk is eliminated which risk management strategy

Question 8 (Mandatory) (1 point) If you change
Question 8 (Mandatory) (1 point) If you change your project management plan in such a way that a risk is eliminated which risk management strategy are you employing? Risk reduction Risk termination Risk mitigation C Risk avoidance