Question: QUESTION 8 Network diagram 1. When is the LS for E. Show all your work Task Duration Predecessor A 5 B 8 A C 3

 QUESTION 8 Network diagram 1. When is the LS for E.

QUESTION 8 Network diagram 1. When is the LS for E. Show all your work Task Duration Predecessor A 5 B 8 A C 3 B 4 5 - Immo 7 IT00000> 6 8 F 6 G 5 HI