Question: QUESTION 8 XYZ is considering a project that is expected to cost 57.100 today, produce a cash flow of 58.200 in 2 years, and have

 QUESTION 8 XYZ is considering a project that is expected to

QUESTION 8 XYZ is considering a project that is expected to cost 57.100 today, produce a cash flow of 58.200 in 2 years, and have an NPV of $300. What is the cost of capital for the project? A rate less than 3.00% or a rate equal to or greater than 15.00% A rate equal to or greater than 3.00% but less than 6.00% A rate equal to or greater than 6.00% but less than 9.0096 A rate equal to or greater than 9.00% but less than 12.00% A rate equal to or greater than 12.00% but less than 15.00%