Question: Question 9 ( 1 point ) Hydro One plans to complete a modification with the project start date of March 1 2 . The procurement

Question 9(1 point)
Hydro One plans to complete a modification with the project start date of March 12. The procurement activities begin on July 6 worth $3.5 million. Calculate the amount the project manager obtains on March 12 to pay for all the procurement, if money is worth 2.5% per year.
a $3,472,175
b $3,497,654
c $3,266,532
d $2,435,642