Question: Question 9 1 pts If a project's network diagram is shown as below (time unit is a week), reducing 1 week from Activity B should

Question 9 1 pts If a project's network diagram

Question 9 1 pts If a project's network diagram is shown as below (time unit is a week), reducing 1 week from Activity B should be able to reduce the project completion time by 1 week. B (5) A (4) E (4) C(2) D (3) O True O False