Question: Question 9 (1.25 points) You are performing MRP calculations for an item that has a lot size of 400 and a two week lead time.

Question 9 (1.25 points) You are performing MRP
Question 9 (1.25 points) You are performing MRP calculations for an item that has a lot size of 400 and a two week lead time. Your net requirement in week in week 6 is 467 units. What should be the amount of your planned order release? 800 O 467 Not enough information is given to determine the planned order release quantity. 400