Question: Question 9 2 points Save Answer Last year, a company reported estimated overhead, $600,000; applied overhead, $550,000; and actual overhead, $538,000. The company's overhead cost
Question 9 2 points Save Answer Last year, a company reported estimated overhead, $600,000; applied overhead, $550,000; and actual overhead, $538,000. The company's overhead cost for the year would be: A) underapplied, $50,000 B) underapplied, $12,000 C) overapplied, $50,000 D) overapplied, $12,000 E) underapplied, $62,000 Enter only the letter of the correct response in the space below (ie. A, B, C, D, or E)