Question: Question 9 3 points (CH 7) Assume that you are the project manager for the construction of a 15 km road. Further assume that the

Question 9 3 points (CH 7) Assume that you are
Question 9 3 points (CH 7) Assume that you are the project manager for the construction of a 15 km road. Further assume that the work is uniformly distributed over 12 weeks. The total approved budget for this project is ALD 600,000. At the end of five three weeks of work, AED 160,000 has been spent, and five km of road have been completed. What is the planned value of the project at this point in time in AED? a. 160,000 b. 200.000 O c. 150,000 Od. 600,000