Question: Question 9 3 pts The lead time used in a MRP plan for in-house production includes: Queue and setup times Wait and move times Actual

Question 9 3 pts The lead time used in a MRP plan
Question 9 3 pts The lead time used in a MRP plan for in-house production includes: Queue and setup times Wait and move times Actual run times O All of the above Question 10 3 pts Which of following data types is NOT required to be maintained accurately for MRP to work well? Facility Capacity Lead times for purchased and produced items Bill of Material Master Production Schedule