Question: Question 9 For a particular project, the relationships between the activities are illustrated in the following network diagram. A D E B. C F--G Which

Question 9 For a particular project, the

Question 9 For a particular project, the relationships between the activities are illustrated in the following network diagram. A D E B. C F--G Which of the following statements is true? O A. Activity D has two predecessors, activity A and activity B. O B. Activity B has two predecessors, activity C and activity D. O c. The completion of activity B marks the end of the project. O D.One must complete activity F to begin activity E