Question: Question 9 If a task in a given project has a criticality index of 9 5 % , what does this number say about that
Question
If a task in a given project has a criticality index of what does this number say about that task?
The duration of that task is likely to be of the overall duration of the project
This task is more critical than of the other tasks in the project
This task occurs before of the other tasks on the critical path
This task is highly likely to be on the critical path of a project and should be monitored closely