Question: question 9 Suppose a project has a positive NPV. What can you say about the project's IRR? IRR will be greater than the cost of
Suppose a project has a positive NPV. What can you say about the project's IRR? IRR will be greater than the cost of capital IRR will be equal to the cost of capital IRR will be less than the cost of capital Not enough information to say anything about IRR