Question: (Question 9-10) Suppose you want to implement a kanban system for Part A, which is produced by WC1, stored in a storage area, and used
(Question 9-10) Suppose you want to implement a kanban system for Part A, which is produced by WC1, stored in a storage area, and used by WC2. Part A is required by WC2 at the rate of 30 units per hour. It is produced and stored by using a container of size 20 units. It takes 2 hours for WC1 to produce a container of Part A. You have decided to set safety stock as 10% of needed inventory.
9.What is the average demand during leadtime?
Group of answer choices
20 units
30 units
40 units
60 units
80 units
10.What should be the number of containers for the storage area?
Group of answer choices
2
3
4
5
6
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock