Question: Question A [AR1: 5 Marks] Consider the projects described in the table below: End of Year Project R Cash Flow ($) Project S Cash Flow
Question A [AR1: 5 Marks]
Consider the projects described in the table below:
| End of Year | Project R Cash Flow ($) | Project S Cash Flow ($) |
| 0 | $90,000 | $90,000 |
| 1 | 17,000 | 0 |
| 2 | 17,000 | 0 |
| 3 | 17,000 | 0 |
| 4 | 17,000 | 0 |
| 5 | 17,000 | 0 |
| 6 | 17,000 | 34,000 |
| 7 | 17,000 | 34,000 |
| 8 | 17,000 | 34,000 |
| 9 | 17,000 | 34,000 |
| 10 | 17,000 | 90,000 |
Both projects have an appropriate risk adjusted discount rate of 7 percent.
Required:
| a. | Calculate the NPV and IRR for both projects |
| b. | If projects R and S are independent, which will you undertake? |
| c. | If projects R and S are mutually exclusive, which will you undertake? |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
