Question: Question A B C D E G H Most Optimistic J 3 5 5 3 1 0 5 1 0 1 0 1 8 Most

Question
A B C D E G H Most Optimistic J 3553105101018 Most Likely 15881015591512 Worst Case Time 203624121522825333230
PERT-MEAN 16.5010.178.179.6715.335.0011.0017.1715.00 SD 21.335.503.171.172.002.001.003.333.833.67 Variance 2.0030.2510.03
1.364.004.001.0011.1114.6913.444.00 Path Mean 129.33 SD 9.6896279
Using the data provided answer the following:
Question 1. Assume that activity A took 20 days to complete. Upon completion of activity A, the project planner wants to determine the probability that project will be completed in 80 day? What is the probability?
Question 2. Assume that activity A took 20 days to complete. Activity times for B, D and F remained unchanged but activity C took 10.2 days to complete. What is the probability that project will be completed in 80 days based on project progress at the end of 30.2 days?
Question 3. Assume that activity A took 16.5 days, B 12 days, F 8 days, and E 10 days. Activity times for C and D remained unchanged. What is the probability that project will be completed in 80 days based on the project progress at the end of 38.5 days?
Question 4. Assume that activities A and B took 16.5 and 10.2 days, respectively. If activity E takes 17 days and H takes 20 days, what is the probability that project will be completed in 80 days upon completion of activity H? What should be the new activity time for activity J to have probability of completion to be .95?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!